Drilling Progress at Citizen Green #1 Well

 

bytes form bit art
Drilling Activity for December 15, 2011

Retrieved drill rod from coring assembly. Made up inner core barrels, placed in drilling assembly, and pumped down into place. Cored from 5,246 to 5,306 ft measured depth (MD)/4,722 to 4,774 ft true vertical depth (TVD). Retrieved and laid down 57.5 ft of recovered core. Inserted drill rod and wiped hole up to 5,000 ft. Drilled from 5,306 to 5,533 ft MD/4,774 to ~4,974 ft TVD. Wiped hole up to 5,000 ft. Surveyed for inclination and azimuth. Drilled from 5,533 to 5,702 ft MD/~4,774 to ~5,123 ft TVD.

Notes/Observations

  • ~TVD depths are based on projected inclination and azimuth

  • Drilling fluid density at 10.1 pounds per gallon

Drilling Activity for December 16, 2011

Drilled from 5,702 to 6,062 ft measured depth (MD)/5,126 to ~5,460 ft true vertical depth (TVD). Surveyed at 5,935 ft MD and wiped hole. Drilled from 6,062 to 6,313 ft MD/~5,460 to ~5,693 ft TVD.

Notes/Observations

  • ~TVD depths are based on projected inclination and azimuth

  • Some drag observed on wiper trip; plan to wipe hole back to previous core point at next wiper trip point

  • Drilling fluid density at 10.1 pounds per gallon

 

 

12-15-16 drill progress