Drilling Progress at Citizen Green #1 Well

 

bytes form bit art
Drilling Activity for December 17, 2011

Drilled from 6,313 to 6,561 ft measured depth (MD)/5,693 to ~5,929 ft true vertical depth (TVD). Surveyed at 6,430 ft MD and wiped hole up to 4,619 ft. Observed 30,000# to 40,000# over pull. Lowered pipe to 5,306 ft. Drill string stuck and no circulation. Raised and lowered string to free pipe and establish circulation. Reamed up and down through tight hole from 5,100 to 5,300 ft. Lowered drill sting back into well and drilled from 6,561 to 6,679 ft MD. Rotary chain broke. Repaired rotary chain.

Notes/Observations

  • ~TVD depths are based on projected inclination and azimuth
  • Drilling fluid density at 10.1 pounds per gallon
Drilling Activity for December 18, 2011

Drilled from 6,679 to 6,973 ft measured depth (MD)/~6,048 to ~6,331 ft true vertical depth (TVD). Penetration rate slowed to less than 10 ft/hour. Circulated drilling fluid to clean hole. Pulled drilling assembly/coring out of the well. Laid down NOV coring assembly and drill collars. Rigged down wireline equipment. Laid down directional drilling assembly. Made up new bit on heavy weight drill pipe (HWDP) in derrick and lowered same into well. Picked up additional HWDP.

Notes/Observations
  • ~TVD depths are based on projected inclination and azimuth
  • Drilling fluid density at 10.2 pounds per gallon
  • Generator for solids control equipment and mud logging trailer failed at midnight; no updated mud log
  • Cores will be shipped to Core Labs today
  • Extremely foggy conditions this morning

 

 