Drilling Activity for July 31, 2009
Well: APS Cholla Pilot Test Well
Rig: WDC Drilling
Activity: Mobilization & Rig Up
Rig-up operations were finalized and a safety audit was conducted by Sandia Technologies, Errol L. Montgomery & Associates, and WDC personnel on July 31, 2009. Drilling operations began at 2:00 p.m.  Drilling progressed from 47 ft to 71 ft.
Observations  
  • Daily activities summarized are from midnight to midnight.
  • 6:00 am August 1, 2009 update: Drilling at 89 ft.
  • Drilling measurements are referenced from the kelly bushing (KB) of Bearcat drilling rig, which will be on site for the deeper portion of the well (12 ft above grade level)
  • Conductor pipe: 14" OD, set at 47 ft below the KB
  • Drilling progressing slowly due to lack of weight on bit.  Rate of penetration will increase as additional drill collars are added to the bottom hole assembly.


 

art art art art
art art
art Click to view more ino on Moenkopi Formation art art
Click to view more info on Coconino Sandstone art
click to view info on Supai Formation art
click to view info about Naco Formation art
Click to view info about Martin Formation art
art art

click here to review an introduction to geologic formations click for more information about Moenkopi Formation click for more info about Moenkopi Formation click for more info on Supai Formation click for more info on Naco Formation click for more info about Martin Formation

 

| Home | Contact Us | ©2004–2022 Frontier Energy, Inc. All Rights Reserved.|